Mobile Release Scheduler: Resource-Constrained Critical Path

A 3D Gantt simulator for a mobile app release plan: watch a resource-constrained project scheduling (RCPSP) list-scheduler assign iOS, Android, backend and QA tasks to limited team capacity, and see how added headcount hits a critical-path floor.

Algorithms & AI3DModerate60 FPS📱 Mobile-adapted
mobile-app-development ↗ Open standalone

A mobile app release plan is a dependency graph, not a checklist: backend APIs must exist before platform teams can build against them, offline sync needs auth, QA needs finished builds, and the store submission needs QA to pass on both platforms. This simulator turns the 13-task release plan into a live 3D Gantt chart and runs a resource-constrained project scheduling (RCPSP) list-scheduler against it — drag the Backend, iOS, Android and QA team-size sliders and watch the schedule re-solve, revealing the point past which extra headcount stops shortening the release and the plan is purely waiting on its critical path.

⚙ Under the hood

A 3D Gantt simulator for a mobile app release plan: a resource-constrained project scheduling (RCPSP) list-scheduler assigns backend, iOS, Android and QA tasks to limited team capacity, revealing the critical-path floor beyond which extra headcount stops shortening the release.

schedulingalgorithmsproject managementcritical pathRCPSPmobile development

3D · Three.js / WebGL renderer · 60 FPS target · runs fully client-side, no install