Time 06:00 f 50.00 Hz Wind 0 MW Solar 0 MW Gas 0 MW Battery 0 MW Demand 0 MW FPS 0
Drag to orbit, wheel or pinch to zoom. Cyan = wind power, yellow = solar, purple = battery, orange = gas, white = demand. The nacelle, battery container and gas turbine hall are cut open; use the view buttons.
Wind, Solar and Battery Grid: Cutaway Lab
3D island grid: a wind farm, solar park, battery yard, substation, gas turbine hall and city. Same live model as the 2D control room: swing equation, droop governors, battery fast response, curtailment.
Pause Reset Quality: High
Overview Nacelle Battery rack Gas turbine Substation
Weather and demand
Battery and grid functions Battery strategy Peak shaving + surplus Flat gas output Manual
Automatic curtailment Secondary control (AGC) Over-frequency droop (50.2 Hz)
Gas units and events
Unit trip Cloud front Wind lull Storm Demand +40 MW Restore shed load
Live readouts
Frequency, last 120 s
Supply and demand, last 24 h
Missions
Independent numerical checks
Controls Drag or one finger: orbit; wheel or pinch: zoom; the five view buttons fly to the nacelle, battery rack, gas turbine and substation. Day speed 120x means a 24 h day takes 12 minutes; frequency physics always runs in real seconds. Unit trip removes the most loaded gas machine; with fast battery response at 0 the frequency may fall below 49 Hz and shed load.
The science
Swing equation. The gas machines hold kinetic energy Ek = sum H S = 3 x 5 s x 110 MVA. A supply-demand mismatch changes it: dEk /dt = ΔP, f = f0 sqrt(Ek /Ek,nom ), i.e. df/dt = f0 ΔP/(2Ek ). Wind, solar and the battery inverter add no inertia unless the battery imitates it.
Droop. Governors: ΔP = -(Δf/f0 ) Pn /R, R = 4 %, 4 s lag; load damping 1.5 %/%. Settled deviation Δf = -ΔP/(sum Pn /(R f0 ) + D); AGC integrates the error to restore 50 Hz.
Wind and solar. P = 1/2 rho A Cp v3 η (96 m rotor, Cp 0.45 < Betz 0.593), rated 3 MW at 11.7 m/s, cut-out 25 m/s. Solar: G = 1098 sin a e-0.057/sin a , clouds G(1 - 0.75 c3.4 ), P = Pstc (G/1000)(1 - 0.0035 (Tc - 25)) 0.87.
Battery. 100 MW / 200 MWh, one-way efficiency sqrt(0.90); fast response P = -K (f - 50 -/+ 0.03). Surplus beyond battery and minimum gas output (3 x 30 MW) must be curtailed.
Simplifications. Single bus, aggregated fleets, simple gas heat rate, illustrative sizes; the 3D diorama is scaled (rotor 52 m) so the machinery fits in view.
Not affiliated with any utility or manufacturer. Typical textbook values.