Net present value. Money later is worth less than money now. Discounting every cash flow at the required return r: NPV = −I + Σt=1..N CFt/(1+r)t, with CFt = CF1(1+g)t−1 and the salvage value added in year N. NPV > 0 means the project beats the hurdle rate.
IRR. The rate that makes NPV exactly zero, found here by bisection. It is the project's own annualised return; compare it with the hurdle rate.
Payback. Years until the running total turns positive (interpolated inside the year). Discounted payback uses present values. Payback ignores everything after it, so it is a liquidity measure, not a value measure.
Closed form (check). For a growing annuity PV = CF1/(r−g) · [1 − ((1+g)/(1+r))N]; the lab compares it with the summed cash flows.
Honest simplifications. Cash flows are certain, annual and end-of-year, with a single constant rate; there is no tax, inflation, financing or option value. The numbers are illustrative; this is not investment advice.