Mode

Live HUD

Project total duration0
Critical-path tasks0
Total slack (non-critical)0
Tasks / Edges0 / 0
σ² (path)0
P(T ≤ deadline)—
Drag a node, or click one and use the slider to change its duration — the forward pass (ES/EF), backward pass (LS/LF) and slack recompute live. Zero-slack tasks form the critical path. In PERT mode each task uses (o, m, p): te=(o+4m+p)/6, σ²=((p−o)/6)².