From seeing the cone to interpreting real measurements
Choose a laboratory below. Your shared Q, T, S, time and distance values remain available as you move between modes. The original 2D and 3D simulations remain separate links.
Q ↓
ALREADY ON MYSIMULATOR
Keep your original visualisations in the family
These links open the existing plan-view and 3D versions in separate tabs.
A vertical slice through the aquifer. The blue line is the piezometric head, not an unconfined water table.
Drawdown at r—
Radial section · schematic, not to scale vertically Aquifer Piezometric head
The Theis solution predicts a head decline that propagates outward from the pumping well. The confined aquifer remains saturated; the pressure surface changes.
Confining layer
Low-permeability material above the aquifer restricts vertical flow in the idealised confined model.
Screened interval
The well screen intersects the aquifer. The ideal Theis solution assumes a fully penetrating well.
Piezometric head
Drawdown is the difference between initial head and pumping head at a given radial distance and time.
MODE 02 · ANALYSE THE EQUATION
Analytical graph laboratory
Explore how drawdown evolves at a monitoring point and how it varies with distance at the selected time.
Drawdown at selected point—
Drawdown vs time
Fixed observation distance · log time axis
s (m)
Drawdown vs distance
Fixed elapsed time · log distance axis
s (m)
WHAT THE CURVES MEAN
The well function controls the shape
For a confined, homogeneous and laterally extensive aquifer under constant-rate pumping, the dimensionless parameter u combines distance, storativity, transmissivity and elapsed time. A smaller u corresponds to a larger well-function value and therefore greater drawdown for the same Q and T.
Current u = — · W(u) = —
MODE 03 · STOP THE PUMP
Pumping-test recovery laboratory
Simulate a constant-rate pumping period followed by pump shutdown. Track residual drawdown as the aquifer recovers.
Residual drawdown now—
Residual drawdown vs time since shutdown
Observation distance uses the shared r parameter · log time axis
s′ (m)
At shutdown, residual drawdown equals the drawdown at the end of pumping. It then declines as the pressure disturbance dissipates.
Recovery superposition: s′ = Q/(4πT) · [W(ut) − W(ut−tₚ)] where t = tₚ + tᵣ. The second term represents an imaginary recharge well switched on at shutdown.
MODE 04 · INTERPRET MEASUREMENTS
Field experiment and parameter estimation
Use a reproducible synthetic pumping-test dataset from five observation wells. Estimate transmissivity and storativity from the measured drawdowns.
Dataset observations40 points
Synthetic field campaign
Reference aquifer: T = 420 m²/day, S = 0.00045. Small deterministic measurement noise is added.
Estimated transmissivityNot fittedRun the estimator to analyse the dataset
Estimated storativityNot fittedRun the estimator to analyse the dataset
Log-space RMSE—Fit quality indicator
Observed vs fitted drawdown
Choose an observation well below
s (m)
Measurement table
All 40 synthetic readings
m
Well radius (m)
Time (d)
Observed s (m)
Educational dataset only. These readings are simulated, not measurements from a real site. Field interpretation should account for well losses, boundaries, partial penetration, heterogeneity and measurement uncertainty.
MODE 05 · SUPERPOSITION
Multiple-well interference
Three pumping wells operate in the same idealised confined aquifer. Their drawdowns add by linear superposition.
Drawdown at centre point—
Plan-view drawdown field · three wells on a line Low → high drawdown
The centre well pumps at Q. Each outer well pumps at the selected fraction of Q. The cross marker is the monitoring point at the centre of the map.
Superposition
For a linear groundwater-flow equation, drawdown from independent wells can be summed at each observation point.
Spacing matters
Closer wells create stronger overlap between cones of depression. Wider spacing can reduce interference at a shared monitoring point.
Design implication
Well-field layout should consider total abstraction, aquifer properties, boundary conditions and neighbouring users.
MODE 06 · APPLY YOUR KNOWLEDGE
Groundwater engineering challenge
Choose a scenario, tune the pumping rate and meet the supply target without exceeding the drawdown limit.
Challenge statusIn progress
MISSION BRIEF
Supply an industrial site
Deliver the required abstraction while protecting a monitoring well 100 m away.
Minimum water demand900 m³/day
Maximum allowed drawdown1.50 m
Monitoring distance100 m
Assessment time30 days
LIVE DESIGN CHECK
—
Predicted drawdown
Water demandPending
Drawdown limitPending
Adjust the shared pumping rate above. Both conditions must be satisfied to complete the mission.
Engineering note: This simplified challenge assumes a single fully penetrating well in a confined, homogeneous, isotropic aquifer of infinite extent. Real well-field design requires site data and a more complete conceptual model.