Annealing controls

Search stats

Current makespan—
Best makespan—
Temperature—
Iteration0
Acceptance rate—
Improvement—

Selected operation

Job / step—
Machine—
Start — End—
Duration—
6 jobs × 5 machines, 30 operations total. Each job visits every machine once in its own random order; a machine runs one operation at a time. A schedule is one ordering of operations per machine — the Gantt chart shows the current schedule discovered by the annealer. Click a bar to inspect that operation. Worse schedules are sometimes accepted (visible as small upward jumps in the raw trace) which is how the search escapes local minima; the bold curve is the best makespan found so far and only ever improves.